England (NHS healthcare premises); Scotland publishes SHTM 06-01 separately

NHS England HTM 06-01 Electrical Services Supply and Distribution (2017 Edition)

122 controls. 2 other frameworks in our corpus share controls with it. Here is all of it, and how much of it you are already doing.

Page built . This page is derived from the framework corpus, which changes when the corpus is extended rather than daily.

122 controls 2 frameworks share controls with it England (NHS healthcare premises); Scotland publishes SHTM 06-01 separately verified against its source document

Every control below is one this framework asks for. The right hand column counts how many other frameworks in our corpus carry the same control, which is the difference between doing this work once and doing it again for the next standard.

There is no implementation kit for this framework yet. The control list and the overlap above are free and complete.

What you already have

Frameworks whose controls overlap this one, most first. If you run any of them, the count is roughly what you have already evidenced.

Every control

CodeControlAlso in
11 Scope, abbreviations and definitions0
10.1-10.16HV switchgear selection, remote switching and emergency power off intertripping0
10.17-10.30HV protection design, grading and review on network change1
10.31-10.48Transformer rating, type, fire compartmentation and temperature monitoring0
10.49-10.51Generator protection tolerant of faults but clearing local cable faults1
10.52-10.76LV switchgear location, access control, circuit charts and discrimination study1
10.77-10.80Network reconfiguration after faults and hard-wired monitored SCADA0
11.1-11.8Battery selection, environment, charging and temperature alarms1
11.10-11.12UPS battery autonomy agreed with clinical stakeholders1
11.16-11.18Battery autonomy for emergency lighting, theatre lamps and fire alarms0
11.19-11.21Generator starting battery capacity and charging1
11.22-11.24Switchgear tripping and closing batteries: 8 hours' autonomy and dual rectifiers0
11.25-11.62UPS configuration, protection, alarms and emergency bypass1
11.63-11.67Central battery units and theatre lamp inverters0
11.9-11.15Split battery banks and string monitoring to allow maintenance on line1
12.1-12.13EMC compliance of the installation and EMC procurement specification0
12.14-12.50EMC zoning, cable segregation and earthing practice0
13.1-13.14Earthing design, HV and LV earth interconnection study and generator earthing0
13.15-13.32Supplementary bonding and equipotential bonding busbar in Group 1 and 2 locations0
13.33-13.61Lightning protection to BS EN 62305 and surge protection devices0
14.1-14.48Containment and cable routes: protection, fire stopping, segregation and HV warnings0
14.49-14.81Cable sizing, fault calculation for primary and secondary supplies, and identification0
15.1-15.5No trailing multi-outlet extension leads in Group 1 and 2 locations; enough fixed outlets0
15.104-15.119Prefabricated wiring systems and BEMS power supplies0
15.14-15.30Medical IT systems in Group 2 locations: monitoring, UPS support and outlet identification0
15.31-15.62Patient environment, outlet placement, imaging supplies, theatre panels and emergency power off0
15.6-15.13RCD protection and dual circuits with secondary supply backing in Medical Locations0
15.63-15.68Continuous supplies, outbuildings, temporary supplies and mobile units0
15.69-15.81Lighting circuits: two sources in grade C and above, secondary supply support and circuit identification0
15.82-15.97Theatre lights and emergency, safety and standby lighting with automatic testing0
15.98-15.103Fire alarm, security, nurse call and blood bank alarms: tertiary supplies and failure alarms0
16.1-16.3Adequate time and resources for validation and commissioning0
16.12Generator operational tests, fuel storage check, records handed over and DNO witness1
16.13-16.16UPS commissioning: changeover, waveform, harmonics, true battery autonomy and alarms1
16.17-16.23Medical IT commissioning and validation including changeover times0
16.24-16.29Fixed wiring verification to BS 7671 by competent persons, including earthing and phase rotation0
16.30-16.32Handover records to be kept0
16.33-16.34Operating and maintenance manual with switching philosophy and isolation points1
16.35-16.36As-installed drawings and schematics at every HV and LV panel0
16.37-16.39Building logbook created or updated0
16.4-16.7Generator factory and site testing including static checks and witnessed dynamic tests1
16.8-16.11Generator voltage regulation, load sharing, parallel operation and PFC isolation verified1
17.0-17.8Maintenance duty, responsibility framework and risk-assessed shutdowns1
17.102-17.105UPS functional tests at least six-monthly and full service tests1
17.106-17.108UPS single-line diagram, site logbook and records of alarms, outages, tests and servicing1
17.109-17.118Medical IT inspection, annual functional tests, changeover verification and records0
17.11-17.21Response to failures: business continuity plans and 24/7 reporting0
17.119-17.127Harmonic filter and power-factor correction maintenance0
17.128-17.138Final circuit inspection and full testing every three to five years0
17.13-17.17Overall maintenance approach agreed at design with review, safe access and recorded sign-off1
17.139-17.140Coordination with dependent services and testing of lighting batteries0
17.141-17.147Portable appliance testing regime, asset register and stored test records0
17.22-17.28Visual inspection feedback, planned preventive maintenance, audits and condition-based replacement1
17.29-17.31Spares strategy and standardised plant; EMC awareness in maintenance1
17.32-17.42Switchgear PPM, HV visual inspections every three months, thermal imaging and partial discharge testing0
17.43-17.50HV switchgear maintenance programme, operational switching, grading review and secondary injection1
17.51-17.62Transformer inspection, annual fluid sampling and earth continuity0
17.63-17.71LV switchgear inspection every six months, annual operation of fuse-switches and test records1
17.72-17.80Earthing maintenance, annual bonding validation, mobile connections and lightning protection tests0
17.81-17.83Monthly on-load generator test of at least one hour including changeover1
17.84Load bank testing with reactive and resistive load where on-load testing is not acceptable1
17.85-17.86Multi-set test loading above 70% and cooling run-on after tests1
17.87-17.91Annual 110% load engine condition test of at least three hours with safety chain tests1
17.9-17.10Trained maintenance staff, Authorised Person checks on contractors and safe systems of work1
17.90Annual test of automatic transfer switchgear and island-mode tests where cover is below 100%1
17.92Reduced test frequency only where parallel operation with the PES exists1
17.93-17.95Weekly visual inspection and three-monthly functional tests of primary and secondary supplies1
17.96-17.97Single-line diagram of primary and secondary supplies and generator run-hour records1
17.98-17.101UPS, inverter and battery monthly visual inspection and data log records1
22 Introduction: structure and voltage bands0
3.12Security specialist input where IT systems control or monitor electrical plant0
3.13-3.17Electrical Safety Group remit, records and minutes0
3.18-3.22Risk assessment process, residual risks and periodic review0
3.2-3.11Electrical Safety Group: constitution, reporting line and authority0
3.23-3.25Contingency where risks are not mitigated, and design for safe maintenance0
3.26Departures from HTM 06-01 recorded and justified0
3.27Final design and residual risks signed off by all stakeholders0
3.3Risk assessments, safe methods of operation and audit of electrical policy0
3.4Board accountability and contractor participation0
4.1Contingency plans for supply failure and relationship with the electricity supplier0
4.18-4.23Supply restoration times for each clinical risk grade1
4.2-4.3Design to minimise single points of failure, including failures of the internal network0
4.24-4.30Business continuity grades: UPS and load management for support services0
4.31-4.39Distribution strategy driven to agreed residual risk, with resilience for testing and maintenance0
4.4-4.17Risk grading of areas for loss of supply (clinical A to E, business I to IV)1
5.0-5.3Early collaboration with the Electrical Safety Group and competent designers0
5.10-5.31Supply capacity, load assessment and growth allowance0
5.39-5.42Design for safe access, maintenance and commissioning0
5.43-5.52Connection of new works to the DNO or the site network0
5.6Fuel stocks for standby generation maintained1
5.9Dual, diverse primary supplies where possible0
6.1-6.19Power quality: power factor, harmonics and generator compatibility0
7.1-7.13Distribution strategy for resilience and secondary supply provision by risk0
7.14-7.19Segregated primary and secondary systems, emergency coupling and diverse routes0
7.20-7.23Two primary connections above 2 MVA and N+1 standby generators kept in readiness1
7.25-7.68HV and LV network configurations matched to assessed risk0
8.1-8.20HV substation and LV switchroom location and construction1
8.21-8.30Access, security and maintenance space in substations and switchrooms1
8.31-8.36Fire precautions and fire extinguishing in substations0
8.37-8.46Switchroom environment, lighting and minimum equipment and notices1
9.1-9.5Secondary power supply strategy agreed by the Electrical Safety Group0
9.12-9.18Secondary supply location and capacity, continuous rating and load shedding schedule1
9.19-9.21Areas supported by the secondary supply decided at design with stakeholders0
9.22-9.27Generator configuration: N+1 best practice and known failure causes1
9.28-9.44Generator operating mode chosen to allow on-load testing (island, short-term or long-term parallel)1
9.45-9.53Mains failure detection and automatic start and connection timing1
9.54Minimum generator run time of 20 minutes after any start1
9.55-9.56Run and stop signals, simulate-mains-failure switches and alarm monitoring1
9.57-9.60Multi-set operation, synchronising time and load-dependent set control1
9.6-9.31Mobile generator plug-in points: connection, earthing, security and response time1
9.61-9.65Mains return delay, load transfer method and cooling run-on1
9.66-9.69Load management of generators during prolonged outages1
9.7-9.11Renewables run only in parallel with the primary supply, with positive isolation0
9.70-9.75Generator, engine and alternator specification: prime rating and load acceptance1
9.76-9.80Starting batteries and chargers kept fully charged and monitored1
9.81-9.84Fuel storage quantities and fuel quality management1
9.85-9.88Fuel transfer, fire dump valves, leak containment and overfill protection1
9.89-9.92Exhaust, noise, operational safety and controlled disposal of consumables1
App1Appendix 1: Maximum interruption times to the primary supply0
App2-3Appendix 2: Sample test record sheets; Appendix 3: Drawing symbols0
App4Appendix 4: Mains extension leads with medical equipment only after competent risk assessment0
introStatus of HTM 06-01 (2017 edition)0

Tell me when NHS England HTM 06-01 Electrical Services Supply and Distribution (2017 Edition) files something new

One email when a public company newly discloses something this framework governs, naming the company and what our corpus says it puts in scope. Nothing else, and one click to stop.

What this page is

A control-level reference for NHS England HTM 06-01 Electrical Services Supply and Distribution (2017 Edition), drawn from our framework corpus. Control codes and titles are references to the standard, not reproductions of it. The overlap counts and the auditor artefacts are our own work and are the part you will not find elsewhere.