Australia

APRA CPS 230 Operational Risk Management

99 controls. 262 other frameworks in our corpus share controls with it. Here is all of it, and how much of it you are already doing.

Page built . This page is derived from the framework corpus, which changes when the corpus is extended rather than daily.

99 controls 262 frameworks share controls with it Australia verified against its source document

Every control below is one this framework asks for. The right hand column counts how many other frameworks in our corpus carry the same control, which is the difference between doing this work once and doing it again for the next standard.

APRA CPS 230 Operational Risk Management Evidence & Implementation Kit

99 controls is the documentation set somebody has to write. This is that set, already written: an adopt-ready artifact for every control in policy and procedure text you edit rather than draft, and the evidence checklist an auditor asks for against each.

See what is in it, $249

The same set every buyer of this kit receives. Nothing here is produced on request.

What you already have

Frameworks whose controls overlap this one, most first. If you run any of them, the count is roughly what you have already evidenced.

Every control

CodeControlAlso in
CPS230-11Identification, Assessment and Management of Operational Risk163
CPS230-13Board Accountability for Operational Risk Management144
CPS230-14Board Setting of Senior Manager Roles and Responsibilities18
CPS230-15Operational Risk Elements of the Risk Management Framework14
CPS230-16Internal Audit Review of the Business Continuity Plan98
CPS230-17Mandatory Minimum Classification of Critical Operations8
CPS230-19Tolerance Levels for Each Critical Operation16
CPS230-20Prevention, Adaptation and Return to Normal Operations16
CPS230-24Design and Embedding of Internal Controls20
CPS230-26Critical Operations Register, Continuity Plan and Activation49
CPS230-27Identification and Escalation of Incidents and Near Misses87
CPS230-33Systematic BCP Testing Program20
CPS230-34Tailoring of the Testing Program15
CPS230-37Service Provider Management Policy101
CPS230-39Register of Material Service Providers17
CPS230-40Mandatory Minimum Classification of Material Service Providers16
CPS230-43Due Diligence Before Entering or Modifying a Material Arrangement19
CPS230-45APRA Access Provisions in Formal Agreements7
CPS230-46Ongoing Risk Management of Each Material Arrangement102
CPS230-47Monitoring and Senior Management Reporting on Material Arrangements16
CPS230-49Internal Audit Review of Proposed Critical Operation Outsourcing80
CPS230-50Formal Agreement Content for Material Arrangements15
CPS230-66Review of Operational Risk Management16
CPS230-8Board Oversight, Approval of the BCP, Tolerance Levels and Service Provider Policy11
CPS230-9Management of the Full Range of Operational Risks16
CPS230-P12Key Principles for Operational Risk, Resilience and Service Providers14
CPS230-P15Precondition for Reliance on a Service Provider16
CPS230-P18Integration with the Risk Management Framework and Recovery Planning10
CPS230-P23Senior Management Information to the Board on Resilience Decisions9
CPS230-P25Information and Technology Capability and Asset Health19
CPS230-P26Assessment of Business and Strategic Decisions on the Risk Profile11
CPS230-P27Comprehensive Assessment of the Operational Risk Profile19
CPS230-P28Risk Assessment Before Providing a Material Service to Another Party8
CPS230-P30Monitoring, Review and Testing of Control Effectiveness20
CPS230-P31Remediation of Material Operational Risk Weaknesses21
CPS230-P33APRA Notification of Operational Risk Incidents within 72 Hours19
CPS230-P40Required Content of the Business Continuity Plan17
CPS230-P41BCP Execution Capability and Tolerance Breach Reporting16
CPS230-P42APRA Notification of Disruption Outside Tolerance within 24 Hours11
CPS230-P45Annual Update of the Business Continuity Plan15
CPS230-P48Required Content of the Service Provider Management Policy15
CPS230-P51Annual Submission of the Material Service Provider Register to APRA3
CPS230-P59APRA Notification of Service Agreements and Offshoring8
1Para 1 Authority0
10Para 10 Adjustments and exclusions0
11Para 11 Key principles: manage operational risk, keep critical operations within tolerance, manage service provider risk1
12Para 12 Identify, assess and manage operational risk2
13Para 13 Prevent disruption, adapt within tolerance and return to normal promptly1
14Para 14 Rely on a service provider only where prudential obligations stay fully met1
15Para 15 Operational risk elements of the risk management framework2
16Para 16 Review operational risk management within the CPS 220 / SPS 220 framework reviews1
17Para 17 Integrate operational risk management; align BCP with recovery and exit planning1
18Para 18 APRA responses to material weaknesses0
19Para 19 Board ultimate accountability for operational risk oversight2
2-5Paras 2 to 5 Application and group application0
20Para 20 Board ensures clear senior manager roles for operational risk, continuity and service providers2
21Para 21 Board oversight duties: risk profile, BCP and tolerances, service provider policy2
22Para 22 Senior management informs the Board on impacts to critical operations1
23Para 23 Manage the full range of operational risks end to end1
24Para 24 Sound information and IT capability; monitor asset age and health; meet CPS 2342
25Para 25 Assess the operational risk impact of business and strategic decisions1
26Para 26 Maintain a comprehensive operational risk profile assessment2
27Para 27 Risk assessment before providing a material service to another party0
28Para 28 Design, implement and embed internal controls2
29Para 29 Monitor, review and test controls; report results; rectify gaps promptly1
30Para 30 Remediate material weaknesses and keep them in the risk profile until fixed2
31Para 31 Identify, escalate, record and address incidents and near misses1
32Para 32 Notify APRA within 72 hours of a material operational risk incident2
33Para 33 Business continuity duties: critical operations register, minimise disruption, credible BCP, activate, return2
34Para 34 Meaning of critical operations0
35Para 35 Minimum set of critical operations unless justified0
36Para 36 APRA may require a critical operation classification0
37Para 37 Tolerance levels for each critical operation2
38Para 38 APRA may require or set tolerance levels0
39Para 39 Required content of the BCP2
40Para 40 Maintain BCP execution capability; monitor tolerances; report breaches to the Board1
41Para 41 Notify APRA within 24 hours of a disruption outside tolerance1
42Para 42 Systematic BCP testing program with an annual exercise2
43Para 43 Tailored test scenarios including material service provider disruption2
44Para 44 Annual BCP update2
45Para 45 Internal audit periodic review and assurance on the BCP2
46Para 46 Comprehensive service provider management policy2
47Para 47 Required content of the service provider policy, including fourth parties2
48Para 48 Register of material service providers and management of their risks1
49Para 49 Minimum material service provider classifications unless justified0
50Para 50 Annual submission of the material service provider register to APRA1
51Para 51 APRA may require a materiality classification0
52Para 52 Due diligence and risk assessment before entering or materially modifying a material arrangement1
53Para 53 Formal legally binding agreement for each material arrangement and its minimum terms1
54Para 54 APRA access, on-site visit and non-impediment clauses1
55Para 55 Manage the risks of each material arrangement, including BCP execution and orderly exit1
56Para 56 APRA may require changes to an arrangement0
57Para 57 Exemption for Attachment-category providers on standardised terms or no formal agreement0
58Para 58 APRA written exemption0
59Para 59 Monitor material arrangements and report to senior management2
6Para 6 Commencement0
60Para 60 Notify APRA of critical-operation agreements (20 business days) and before material offshoring1
61Para 61 Internal audit review of critical-operation outsourcing and reporting to the Board0
7-9Paras 7 to 9 Interpretation0

Tell me when APRA CPS 230 Operational Risk Management files something new

One email when a public company newly discloses something this framework governs, naming the company and what our corpus says it puts in scope. Nothing else, and one click to stop.

What an auditor will ask you to produce

The artefacts named on the failure modes this framework speaks to.

  • Role inventory + RACI
  • Metrics + management review
  • Annual cycle documentation
  • Supervisory dialogue records
  • Role inventory + RACI + DPO designation
  • Operational controls + tooling investment
  • Mapping of people/tech/info/provider dependencies
  • action plan with owners and dates
  • dependency map
  • success indicators

How programmes fail on this

Failure modes named by this framework and others. Each opens the full record.

What this page is

A control-level reference for APRA CPS 230 Operational Risk Management, drawn from our framework corpus. Control codes and titles are references to the standard, not reproductions of it. The overlap counts and the auditor artefacts are our own work and are the part you will not find elsewhere.

Measure this against what you already run · All frameworks · Today's edition