1 | Scope and purpose: requirements for an OSHMS and a sustainable safety and health culture, integrable with other management systems, without performance criteria or design specifica | 0 |
2 | Terms and definitions (active and reactive monitoring, arrangements, audit, competent person, hazard, incident, near miss, OSHMS, risk, risk assessment, safety and health committee | 0 |
3 | The employer owns OSH and legal compliance, shows strong leadership and commitment, and sets up an OSHMS containing policy, organising, planning and implementation, evaluation and | 0 |
3.1.1 | A written OSH policy, set with employees and their representatives, specific, concise, signed, communicated, reviewed and available, committing to protection, prevention, complianc | 0 |
3.1.2 | Employee participation: consultation, information and training on all OSH aspects including emergencies, active participation arrangements, and a functioning safety and health comm | 0 |
3.2.1 | Allocated responsibility, accountability and authority for the OSHMS, documented and communicated duties for all personnel, adequate resources, and a senior-level OSH management re | 0 |
3.2.2 | Defined OSH competence requirements, access to sufficient competence, and training needs identified, delivered and recorded for all members of the organisation | 0 |
3.2.3 | OSHMS documentation covering policy, objectives, roles, significant hazards and their controls and procedures, kept clear, current, accessible and controlled, with identifiable, re | 0 |
3.2.4 | Communication arrangements for receiving, documenting and answering OSH communications, internal flow across levels and functions including contractors, vendors and visitors, and h | 0 |
3.3.1 | An initial review of the existing OSHMS and arrangements by the employer with competent persons and employees, documented, used as the planning basis and the baseline for improveme | 0 |
3.3.2 | Measurable OSH objectives consistent with the policy and reviews: specific, lawful, focused on continual improvement, realistic, documented, communicated, evaluated and updated | 0 |
3.3.3.1 | Hazard identification: documented procedures, with employee participation, covering all employees and persons at the workplace and routine, non-routine and abnormal activities, fin | 0 |
3.3.3.2 | Risk assessment: estimate and evaluate the risk level of each identified hazard and use the result for decisions and for determining controls | 0 |
3.3.3.3 | Risk control in the order elimination, control at source, safe systems of work and administrative measures, then a personal protective equipment programme for residual risk, implem | 0 |
3.3.3.4 | HIRARC procedures adapted to the organisation's hazards, regularly reviewed, compliant with law and good practice, and informed by current knowledge from authorities and competent | 0 |
3.3.4 | Documented emergency prevention, preparedness and response arrangements that identify potential emergencies, involve external services, are tested where practicable and reviewed af | 0 |
3.3.5 | Management of change: evaluate OSH impacts of internal and external changes beforehand, carry out hazard identification and risk assessment before new methods, materials, processes | 0 |
3.3.6 | Procurement: documented procedures so that OSH requirements are identified, evaluated and built into purchasing and leasing specifications, and legal requirements are identified an | 0 |
3.3.7 | Contracting: arrangements so that the organisation's safety and health requirements, or at least equivalent ones, apply to contractors and their employees | 0 |
3.4.1 | Performance monitoring and measurement: regular, reviewed arrangements with allocated responsibility, indicators matched to size, activity and objectives, qualitative and quantitat | 0 |
3.4.2 | Incident investigation: documented procedures that find OSHMS failures, notification to authorities where required, competent investigators with employee participation, documented | 0 |
3.4.3 | Periodic OSHMS audits under documented procedures and an audit programme (auditor competence, scope, method, reporting), by competent independent persons, with results communicated | 0 |
3.4.4 | Top management review of OSHMS suitability, adequacy and effectiveness, at a planned frequency and scope, with findings recorded, documented and communicated | 0 |
3.5.1 | Preventive and corrective action arising from monitoring, audits and management review, applied by recognised control measures, completed and documented in a timely manner when con | 0 |
3.5.2 | Arrangements for the continual improvement of the relevant OSHMS elements | 0 |